Restaurant Fit-Out Checklist: From Bare Shell to Opening

This checklist focuses on physical delivery: what needs to be verified, installed, tested and handed over. For the wider project scope, including the business brief, design approvals and who is responsible for each work package, explore FlatPackCo’s Restaurant Design & Build service.

Tick items as you go. Your ticks stay on this device.

A. Site & Landlord

B. Electrical

Electrician checking a restaurant electrical distribution board with a multimeter
Confirm the available load before the kitchen, HVAC and signage loads are fixed.

C. Plumbing & Drainage

D. HVAC, Exhaust & Fresh Air

Contractor pointing out the kitchen exhaust duct and electrical points to a restaurant owner on site
Agree the exhaust route and discharge point before the ceiling design is fixed.

E. Fire & Life Safety

F. Kitchen & BOH

For layout and equipment planning, see our commercial kitchen guide.

G. FOH Layout

H. Interior Finishes

Our flooring and wall panelling guides cover material choices.

Terrazzo, fluted timber, brass and fabric samples laid out on a table for approval
Approve physical samples and confirm availability before ordering.

I. Furniture, Counters & Joinery

See the restaurant furniture guide for sizing and materials.

J. Lighting & Signage

Read more in our lighting and signage guides.

K. Procurement

L. Site Execution

Electrician, plumber and tiler working at the same time on a restaurant fit-out
With several trades on site at once, the latest drawing revision has to reach everyone.

M. Testing & Handover

N. Opening Readiness

Newly completed small restaurant on a city street at early evening with warm lights on and tables set
Opening readiness goes beyond handover: commissioning, training, stock and a trial run.

Common Fit-Out Mistakes

  • Starting site work before coordinated drawings are ready
  • Freezing finishes before checking availability
  • Changing kitchen equipment after services are installed
  • Comparing quotes with different scopes
  • Closing ceilings before service checks
  • Installing furniture too early
  • Treating handover as identical to operational opening

Comparing quotes with different scopes is the most common budgeting trap. Our restaurant design and build cost guide lists what each quote should state.

How This Checklist Connects to Design & Build

The fit-out checklist focuses on site delivery. For the broader decisions covering business brief, responsibilities, design approvals, procurement and manufacturing governance, see how the restaurant design and build process works.

Our Restaurant Fit-Out Guide explains fit-out as the physical stage that brings an approved restaurant design to life through construction, custom manufacturing and installation.

Frequently Asked Questions

What is a restaurant fit-out checklist?

A restaurant fit-out checklist tracks the site, kitchen, building services, interiors, installation and testing needed to prepare a commercial space for restaurant operations.

When should you use a restaurant fit-out checklist?

Start during site feasibility to flag constraints. Update it before construction to confirm the scope and responsibilities, then use it during inspections, snagging and handover to track outstanding items.

What is the difference between a restaurant fit-out checklist and a design and build checklist?

A fit-out checklist focuses on site readiness, construction, installation and testing. A design and build checklist covers the wider project, including the business brief, design approvals, procurement and responsibility for each work package.

When should kitchen equipment be finalised for a restaurant fit-out?

Confirm equipment models, dimensions and utility requirements before finalising service layouts or releasing counters for fabrication. Late substitutions can affect power, water, drainage, gas, exhaust and equipment clearances.

What should be checked before closing a restaurant ceiling?

Have the relevant trades inspect concealed services against the latest approved drawings. Check ductwork, electrical cabling, cable trays, lighting connections, sprinklers, detectors and maintenance access where applicable. Record any required inspections or tests before closure.

Is restaurant fit-out handover the same as opening day?

No. Depending on the agreed scope, equipment commissioning, operating approvals, POS setup, staff training, stocking and trial operations may still need to be completed before opening.